CIV E 445 - APPLIED HYDROLOGY SPRING 2008 HOMEWORK 10, CHAPTER 8
Problem 10-1 Route the following triangular inflow hydrograph through a linear reservoir: peak inflow = 240 m3/s, baseflow = 0 m3/s, time-to-peak = 6 h, time base = 16 h, storage constant K = 2 h, and time interval Δt =1 h. Use either a spreadsheet or ONLINE ROUTING 01. Problem 10-2 Solve Problem 10-1 by the storage indication method. Use either a spreadsheet or ONLINE ROUTING 02. Problem 10-3
Determine the actual freeboard for the following dam, reservoir, and flood conditions: dam crest elevation = 125 m; emergency spillway crest elevation = 120 m; coefficient of spillway rating = 1.7; exponent of rating = 1.5; width of emergency spillway (rectangular cross section) = 18 m.
Inflow hydrograph to reservoir:
Assume the initial reservoir pool level at spillway crest. Use ONLINE ROUTING 03. Problem 10-4 Design the emergency spillway width (rectangular cross section) for the following dam, reservoir, and flood conditions: dam crest elevation = 483 m; emergency spillway crest elevation = 475 m; coefficient of spillway rating = 1.7; exponent of spillway rating = 1.5. Elevation-storage relation:
Inflow hydrograph to reservoir:
Assume design freeboard = 2 m and initial reservoir pool level at spillway crest. Use ONLINE ROUTING 03. [Hint: Try several values of spillway length L (width). Use accuracy of 0.1 m]. |